LIST OF Under Progress MACRO WORKS

  Workcode Taluka Type Subtype Category Work Name Agency Plan Approved Date Allocation ADM Approved Date ADM Amount Work Order Amt Exp Stages of Work Status Updated On
 
Sl.NoWorkcodeTal_NameSub TypeSectorCategoryWORK NAMEAGENCY NAMEPlan App DATEAllocationAdm APP DateADM AmtWO AmtEXPStages of workStatus Type NameLast Modified
1 KPL15R1121023KushtagiInfrastructureWater SupplySCP Water Purification plant at Kalmalli- Pre-fab-hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:29:33 PM
2 KPL15R1121024KushtagiInfrastructureWater SupplySCP Water Purification plant at Kalmalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:08:16 PM
3 KPL15R1121025KushtagiInfrastructureWater SupplySCP Water Purification plant at Tavargera - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:30:31 PM
4 KPL15R1121026KushtagiInfrastructureWater SupplySCP Water Purification plant at Tavargera - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:09:58 PM
5 KPL15R1121027KushtagiInfrastructureWater SupplySCP Water Purification plant at Myadardokki - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:30:52 PM
6 KPL15R1121028KushtagiInfrastructureWater SupplySCP Water Purification plant at Myadardokki - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:11:07 PM
7 KPL15R1123029KushtagiInfrastructureWater SupplyGENERALWater Purification plant at K.Boduru - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:31:14 PM
8 KPL15R1123030KushtagiInfrastructureWater SupplyGENERALWater Purification plant at K.Boduru - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:12:53 PM
9 KPL15R1123031KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Julakatti - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:31:34 PM
10 KPL15R1123033KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Santebazar of Hanumsagar - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:31:53 PM
11 KPL15R1123034KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Santebazar of Hanumsagar - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.78Work Under ProgressUnder Progress11/15/2017 12:07:24 PM
12 KPL15R1123035KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Hanamansagar- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:32:14 PM
13 KPL15R1123036KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Hanamansagar-Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:14:29 PM
14 KPL15R1123037KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Hanananal- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:32:37 PM
15 KPL15R1123038KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Hanumanal- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:15:41 PM
16 KPL15R1123039KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Koradkera - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:33:10 PM
17 KPL15R1123041KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Dotihal- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:33:30 PM
18 KPL15R1123042KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Dotihal- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.78Work Under ProgressUnder Progress11/15/2017 1:01:05 PM
19 KPL15R1123043KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Hesarur- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:33:51 PM
20 KPL15R1123044KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Hesarur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under progressUnder Progress11/15/2017 1:17:37 PM
21 KPL15R1123045KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Amrapur - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:34:11 PM
22 KPL15R1123046KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Amrapur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:18:59 PM
23 KPL15R1123047KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Jahagir Guddur - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:34:36 PM
24 KPL15R1123048KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Jahagir Guddur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.78Work Under ProgressUnder Progress11/15/2017 1:02:17 PM
25 KPL15R1123049KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Pattalchinti- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:34:59 PM
26 KPL15R1123050KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Pattalchinti- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:21:03 PM
27 KPL15R1123051KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Badimanal - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:35:21 PM
28 KPL15R1123052KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Badimanal - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.78Work Under ProgressUnder Progress11/15/2017 1:03:27 PM
29 KPL15R1123053KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Kallagonal- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:35:41 PM
30 KPL15R1123054KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Kallagonal- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:21:59 PM
31 KPL15R1123055KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Garjanal - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:36:01 PM
32 KPL15R1123056KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Garjanal - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.00Work Under ProgressUnder Progress11/15/2017 1:22:59 PM
33 KPL15R1123057KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Kidadur - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:36:21 PM
34 KPL15R1123058KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Kidadur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.78Work under ProgressUnder Progress11/15/2017 1:04:46 PM
35 KPL15R1123059KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Kushtagi town ward no.1 Slum Board colony- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 1:36:42 PM
36 KPL15R1123060KushtagiInfrastructureWater SupplyGENERALWater Purification plant at Kushtagi town ward no.1 Slum Board colony- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 15/11/20162.471.470.57Work under progressUnder Progress11/15/2017 1:07:05 PM
37 KPL15R4121077KoppalInfrastructureWater SupplySCP Water Purification plant at Hitnal - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:25:43 PM
38 KPL15R4121079KoppalInfrastructureWater SupplySCP Water Purification plant at Kawluru - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:30:09 PM
39 KPL15R4121081KoppalInfrastructureWater SupplySCP Water Purification plant at Ajlapur- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:31:08 PM
40 KPL15R4123007KoppalInfrastructureRoads & BridgesGeneralವಾರ್ಡ ನಂ.13ರಲ್ಲಿ ಸುಭಾಷ ಜೋಗಿ ಇವರ ಮನೆಯಿಂದ ಮದರ್ಾನಪ್ಪ ಅಳ್ಳಳ್ಳಿ ಮನೆಯವರೆಗೆ ಹಾಗೂ ಬಾಬುಸಾಬ ಕೊತ್ವಾಲ್ ಇವರ ಮನೆಯಿಂದ ಗವಿಸಿದ್ದೇಶ್ವರ ಕಾಲೇಜ್ ಕಂಪೌಂಡ್ವರೆಗೆ ಸಿಸಿ ರಸ್ತೆ ಕಾಮಗಾರಿ ನಿರ್ಮಾಣKRIDL19/09/2016 14.50 19/09/201614.500.0010.0090 ಮೀ ಸಿ.ಸಿ ರಸ್ತೆ ಕಾಮಗಾರಿ ಪೂರ್ಣಗೊಂಡಿದೆUnder Progress8/28/2017 10:41:40 AM
41 KPL15R4123015KoppalInfrastructureRoads & BridgesGeneralವಾರ್ಡ ನಂ.28ರಲ್ಲಿ ಕಾಳಿದಾಸ ನಗರದಲ್ಲಿ ಲಕ್ಷ್ಮವ್ವ ಕನಕಗಿರಿ ಇವರ ಮನೆಯಿಂದ ಮಂಜು ಕಿತ್ತೂರು ಇವರ ಮನೆಯವರೆಗೆ ಹಾಗೂ ಮಂಜು ಸಜ್ಜನ್ ಇವರ ಮನೆಯಿಂದ ಹಿರೆವಳಿ ಹೊಲದವರೆಗೆ ಹಾಗೂ ಶಕೀಲ್ ಮನೆಯಿಂದ ಹಿರೆವಳಿ ಇವರ ಹೊಲದವರೆಗೆ ಸಿಸಿ ರಸ್ತೆ ಹಾಗೂ ಆರ್.ಸಿ.ಸಿ. ಚರಂಡಿ ನಿರ್ಮಾಣ ಕಾಮಗಾರಿKRIDL19/09/2016 15.93 19/09/201615.930.008.00ಸಿಸಿ ಚರಂಡಿ ಕಾಮಗಾರಿ ಪೂರ್ಣಗೊಂಡಿದ್ದು, 150 ಮೀ ಭೂಮಿ ಸಮತಟ್ಟು ಮಾಡಿ ಗ್ರಾವೆಲ್ ಹಾಕಲಾಗಿದೆ ಸಿಡಿ ಕೆಲಸ ಪೂರ್ಣಗೊಂಡಿದ್ದುUnder Progress8/28/2017 10:51:27 AM
42 KPL15R4123061KoppalInfrastructureWater SupplyGENERALWater Purification plant at Kerehalli - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:32:07 PM
43 KPL15R4123063KoppalInfrastructureWater SupplyGENERALWater Purification plant at Chukankal- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:33:25 PM
44 KPL15R4123065KoppalInfrastructureWater SupplyGENERALWater Purification plant at Mundargi- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:33:59 PM
45 KPL15R4123067KoppalInfrastructureWater SupplyGENERALWater Purification plant at Hosa Kankapur- Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:34:36 PM
46 KPL15R4123069KoppalInfrastructureWater SupplyGENERALWater Purification plant at Gabburu - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:35:10 PM
47 KPL15R4123071KoppalInfrastructureWater SupplyGENERALWater Purification plant at Guladahalli - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:35:49 PM
48 KPL15R4123073KoppalInfrastructureWater SupplyGENERALWater Purification plant at Belagatti - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:36:37 PM
49 KPL15R4123075KoppalInfrastructureWater SupplyGENERALWater Purification plant at Mahmadnagar - Pre-fab hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00 Under Progress11/14/2017 12:37:08 PM
         150.42 72.4224.9922.47