LIST OF Under Progress MACRO WORKS

  Workcode Taluka Type Subtype Category Work Name Agency Plan Approved Date Allocation ADM Approved Date ADM Amount Work Order Amt Exp Stages of Work Status Updated On
 
Sl.NoWorkcodeTal_NameSub TypeSectorCategoryWORK NAMEAGENCY NAMEPlan App DATEAllocationAdm APP DateADM AmtWO AmtEXPStages of workStatus Type NameLast Modified
1 BDR15R3113039HumnabadInstitutionalEducationGeneralConstruction of 02 additional rooms to Govt, SC Primetric Boys hostel at Manna-E-KhalliPRED 31/03/2016 20.00 16/08/201620.2618.255.10ground floor roof laid & first floor lintel levelUnder Progress11/18/2017 10:52:25 AM
2 BDR15R3113041HumnabadInstitutionalEducationGeneralConstruction of 02 rooms to Govt. MPS at BemelkhedaPRED 31/03/2016 13.00 02/11/201613.0011.870.00Finishing work is in progressUnder Progress11/18/2017 10:52:51 AM
3 BDR15R3123079HumnabadInfrastructureWater SupplyGENERALWater purification plant in Neerna - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:49:50 AM
4 BDR15R3123080HumnabadInfrastructureWater SupplyGENERALWater purification plant in Bemalkheda - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:50:25 AM
5 BDR15R3123081HumnabadInfrastructureWater SupplyGENERALWater purification plant in Changlera - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:50:43 AM
6 BDR15R3123082HumnabadInfrastructureWater SupplyGENERALWater purification plant in Boral - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:51:05 AM
7 BDR15R3123083HumnabadInfrastructureWater SupplyGENERALWater purification plant in Bhadrapur - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:51:20 AM
8 BDR15R3123084HumnabadInfrastructureWater SupplyGENERALWater purification plant in Karpakpalli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:52:11 AM
9 BDR15R3123085HumnabadInfrastructureWater SupplyGENERALWater purification plant in Manna-e-khelli- Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:52:28 AM
10 BDR15R3123086HumnabadInfrastructureWater SupplyGENERALWater purification plant in Karkanalli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:52:42 AM
11 BDR15R3123087HumnabadInfrastructureWater SupplyGENERALWater purification plant in Devgiri thanda - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:54:01 AM
12 BDR15R3123088HumnabadInfrastructureWater SupplyGENERALWater purification plant in Vithalapur - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:54:36 AM
13 BDR15R3123089HumnabadInfrastructureWater SupplyGENERALWater purification plant in Govind thanda - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:55:37 AM
14 BDR15R3123090HumnabadInfrastructureWater SupplyGENERALWater purification plant in Bannalli- Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:55:52 AM
15 BDR15R3123091HumnabadInfrastructureWater SupplyGENERALWater purification plant in Mangalagi- Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/71/2016-17/1722 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:56:13 AM
16 BDR15R4113027BidarInstitutionalEducationGeneralConstruction of 01 additional class room to Govt. NelwadPRED 31/03/2016 6.50 16/08/20166.625.832.40Nearing completionUnder Progress11/13/2017 5:27:38 PM
17 BDR15R4123005BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road from H/o Maqeet operator to Hyderabad road in ward No. 33TMC Bidar 08/02/2016 10.00 12/09/20169.700.000.00Formation work is Completed, GSB & M20 is nearing completionUnder Progress12/14/2017 12:19:56 PM
18 BDR15R4123008BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road from H/o Dilip to H/o Srimandal at vidya nagar in ward No. 25TMC Bidar 08/02/2016 10.00 12/09/20169.769.760.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be end of January 2018Under Progress12/14/2017 12:18:36 PM
19 BDR15R4123009BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road & Drain from H/o laiq Moulsab to H/o Muneer Sir at Malgounda colony in ward No. 25TMC Bidar 08/02/2016 10.00 12/09/20169.230.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be 15th december 2017)Under Progress12/13/2017 7:48:48 PM
20 BDR15R4123010BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road & Drain from H/o Asif to H/o Jameel at ahmed colony in ward No. 25TMC Bidar 08/02/2016 10.00 12/09/201610.160.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be 15th december 2017)Under Progress12/13/2017 7:49:15 PM
21 BDR15R4123011BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road & Drain from Masjid Mehraj to H/o Tabrez Wasi at Mehraj colony in ward No. 25TMC Bidar 08/02/2016 10.00 12/09/201610.140.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be 15th december 2017)Under Progress12/13/2017 7:49:43 PM
22 BDR15R4123012BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road from H/o Rasool Sab to H/o Mateen at Haq colony in ward No. 25TMC Bidar 08/02/2016 10.00 12/09/20169.630.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be completed end of January 2018)Under Progress12/14/2017 12:22:29 PM
23 BDR15R4123013BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road & Drain from H/o Naseer to Masjid Aqsa at Haq colony in ward No. 25TMC Bidar 08/02/2016 15.00 12/09/201615.210.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be completed end of january 2018Under Progress12/14/2017 12:20:54 PM
24 BDR15R4123014BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road from H/o Akheel to H/o Idress at Haq colony in ward No. 25TMC Bidar 08/02/2016 15.00 12/09/201615.210.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be completed end of January 2018)Under Progress12/14/2017 12:22:03 PM
25 BDR15R4123015BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road from Sony Ice Cream to H/o Mallappa House at Haq colony in ward No. 25TMC Bidar 08/02/2016 10.00 12/09/201610.130.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be completed end of January 2018)Under Progress12/14/2017 12:22:55 PM
26 BDR15R4123016BidarInfrastructureRoads & BridgesGeneralConstruction of CC Road from H/o yaser to KEB Contractor at Bilal Colony in ward No: 25TMC Bidar 08/02/2016 10.00 12/09/201610.130.000.00Work is held up due to ongoing UGD work under AMRUT Scheme (Excepted date of commencement is would be completed end of January 2018)Under Progress12/14/2017 12:23:35 PM
27 BDR15R4123021BidarInfrastructureRoads & BridgesGeneralImprovements of road from Aurad (S) to Sirsi(A) in Bidar TalukaPWD 31/03/2016 107.28 03/10/2016104.0087.120.00WMM completed B M to be done Work will be completed by Dec 2017Under Progress11/13/2017 5:33:08 PM
28 BDR15R4123046BidarInfrastructureWater SupplyGENERALWater purification plant in Mandakanalli - Pre-fab Hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/69/2016-17/1721 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress11/1/2017 11:05:43 AM
29 BDR15R4123048BidarInfrastructureWater SupplyGENERALWater purification plant in Anadoor- Pre-fab Hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00ಸಂ:ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/69/ 2016-17/1721 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:39:50 AM
30 BDR15R4123050BidarInfrastructureWater SupplyGENERALWater purification plant in Bhairanlli - Pre-fab Hut (4.88m x 9.76m)KRIDL26/05/2016 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/69/2016-17/1721 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:40:47 AM
31 BDR15R4713014Bidar InstitutionalHealthGeneralProcurement for Items for Hospitals of Bidar District -ind 97HKRDB22/04/2016 30.37 22/04/201630.370.0021.20 Under Progress11/1/2017 12:17:54 PM
32 BDR15R4713018Bidar InstitutionalHostelGeneralfurnitures for BCM Hostels in Bidar - Ind 103HKRDB05/02/2016 150.41 05/02/2016150.410.0064.80under progressUnder Progress10/31/2017 5:13:09 PM
33 BDR15R5123023BasvakalyanInfrastructureRoads & BridgesGeneralImprovements and widing road Koudiyal to Nagoba Katta in Basavakalyan talukaPWD 05/08/2016 73.88 05/08/201673.8863.7430.00GSB Completed, Work will be completed by dec 2017Under Progress12/6/2017 1:17:51 PM
34 BDR15R5123052BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Ujalamb - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:43:37 AM
35 BDR15R5123053BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Bhosga - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:43:59 AM
36 BDR15R5123054BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Maisalga - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:44:29 AM
37 BDR15R5123055BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Manthal - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:45:03 AM
38 BDR15R5123056BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Kohinoor - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:45:21 AM
39 BDR15R5123057BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Belura - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:45:41 AM
40 BDR15R5123058BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Ghotala - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:46:01 AM
41 BDR15R5123059BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Jajanmugli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:46:23 AM
42 BDR15R5123060BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Gadigoundgaon - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:46:41 AM
43 BDR15R5123061BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Kumbargalli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:46:59 AM
44 BDR15R5123062BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Helawa Galli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:47:24 AM
45 BDR15R5123063BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Kaikadi Galli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:47:40 AM
46 BDR15R5123064BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Dhor Galli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:47:57 AM
47 BDR15R5123065BasvakalyanInfrastructureWater SupplyGENERALWater purification plant in Waddar Galli - Pre-fab Hut (4.88m x 9.76m)KRIDL16/10/2017 2.60  0.000.000.00ಸಂ: ಹೈಕಮಂ/ಯೋಶಾ/ಮ್ಯಾಕ್ರೋ/70/2016-17/1720 ದಿ: 16.10.2017 ರನ್ವಯ ಕಾಮಗಾರಿಯ ಅನುಷ್ಠಾನ ಇಲಾಖೆ ಬದಲಾವಣೆ ಮಾಡಲಾಗಿದೆ.Under Progress12/16/2017 11:48:11 AM
         589.44 507.84196.57123.50