LIST OF Under Progress MACRO WORKS

  Workcode Taluka Type Subtype Category Work Name Agency Plan Approved Date Allocation ADM Approved Date ADM Amount Work Order Amt Exp Stages of Work Status Updated On
 
Sl.NoWorkcodeTal_NameSub TypeSectorCategoryWORK NAMEAGENCY NAMEPlan App DATEAllocationAdm APP DateADM AmtWO AmtEXPStages of workStatus Type NameLast Modified
1 BRD152123005BhalkiInfrastructureUrban InfrastructureGeneralNemmadi Uru Bhalki: Town HallPWD20/05/2016 199.40 20/05/2016199.40192.3620.90Foundation levelUnder Progress11/8/2017 11:11:27 AM
2 BRD152123007BhalkiInfrastructureUrban InfrastructureGeneralConstn of walkway path to Bhalki Minor Irrigation tank in Bidar DistMI 02/02/2016 198.76 02/02/2016198.76196.69154.96Work in ProgressUnder Progress12/9/2017 11:58:29 AM
3 BRD152123009BhalkiInfrastructureUrban InfrastructureGeneralProviding Chain link fencing to the Bhalki Minor Irrigation tank in Bidar DistMI 02/02/2016 109.09 02/02/2016109.09107.19101.95work in ProgressUnder Progress12/9/2017 11:59:22 AM
4 BRD152123010BhalkiInfrastructureUrban InfrastructureGeneralConstn of Approach road to Bhalki Minor Irrigation tank from PWD main road in Bidar DistMI 02/02/2016 19.78 02/02/201619.7816.998.94Work in Progress.Under Progress11/4/2017 12:50:25 PM
5 BRD154113011BidarInstitutionalEducationGeneralProviding water supply to university campus at nirmanahalli in bidar district from bidar water treatment plant at nirmanahalli tandaRWS04/07/2015 36.50  0.000.000.00under progressUnder Progress 
         563.53 527.03513.23286.75