1 BLY172123017H.B.HalliInfrastructureUrban InfrastructureGENERALProviding 1.8 cum ACE hopper tipper BS 4 to TMC H.B.halli & TMC SiraguppaHKRDB19/10/2017 25.00  0.000.0017.63Completed 75 % payment madeCompleted10/31/2017 12:46:17 PM
2 BLY172123020BellaryInfrastructureWater SupplyGENERALFeeding water to Holagundi tank by raising main from Hadagali branch canal off taking @ch 22.50km and natural nala of HuvinahadagaliKNNL SLIS Hadagali  81.00 19/04/201780.8473.210.00work physically completedCompleted10/27/2017 12:37:30 PM
         106.00 80.8473.2117.63