LIST OF Under Progress MACRO WORKS

  Workcode Taluka Type Subtype Category Work Name Agency Plan Approved Date Allocation ADM Approved Date ADM Amount Work Order Amt Exp Stages of Work Status Updated On
 
Sl.NoWorkcodeTal_NameSub TypeSectorCategoryWORK NAMEAGENCY NAMEPlan App DATEAllocationAdm APP DateADM AmtWO AmtEXPStages of workStatus Type NameLast Modified
1 BLY161113027SirguppaInstitutionalEducationGeneralConstruction of Urdu School and Toilet Block at Sirguppa TownNK09/02/2017 70.00 09/02/201770.0070.0017.00Roof levelUnder Progress11/24/2017 1:53:03 PM
2 BLY161113028SirguppaInstitutionalEducationGeneralConstruction of Two Class Rooms To Govt PU College Tekkalakote, Siruguppa Taluk, Bellary District.NK03/09/2016 16.35 03/09/201616.3516.3511.79Roof completedUnder Progress11/22/2017 11:48:07 AM
3 BLY161113029SirguppaInstitutionalEducationGeneralConstruction of First Floor Laboratory To Govt PU College Tekkalkote, Siruguppa Taluka, Bellary District.NK03/09/2016 13.29 03/09/201613.2913.290.76column raised work under progressUnder Progress11/22/2017 11:48:16 AM
4 BLY161113030SirguppaInstitutionalEducationGeneralConstrution of Ground floor Laboratory To Govt PU College Tekkalakote, Sirugappa Taluka, Bellary District.NK03/09/2016 16.98 03/09/201616.9816.985.26Roof completedUnder Progress11/22/2017 11:48:24 AM
5 BLY161113031SirguppaInstitutionalEducationGeneralConstruction of One Class Room To Govt Pu College Tekkalakote, Siruguppa Taluka, Bellary District.NK03/09/2016 9.12 03/09/20169.129.123.90Roof LaidUnder Progress11/22/2017 11:48:34 AM
6 BLY161113032SirguppaInstitutionalEducationGeneralConstruction of One class Class Room To Govt PU college Tekkalakote, Siruguppa Taluka, Bellary District.NK03/09/2016 9.12 03/09/20169.129.120.65column erection work under progress Under Progress11/22/2017 11:48:45 AM
7 BLY161113033SirguppaInstitutionalEducationGeneralConstruction of Toilet Block To Govt PU College @Tekkalakote, Siruguppa Taluk, Bellary DistrictNK03/09/2016 16.04 03/09/201616.0416.046.29finishing stageUnder Progress11/22/2017 11:48:53 AM
8 BLY162113001BellaryInstitutionalSocialGeneralM.Y Ghorpade G. P Building at B D halli in Bellary talukaNK27/10/2016 50.00 03/02/201750.0050.0011.81Plinth completedUnder Progress11/22/2017 11:54:36 AM
9 BLY162113025BellaryInstitutionalEducationGeneralConstruction of Government PU College at Kurugodu Bellary (D)NK30/12/2016 196.22 30/12/2016196.22196.2234.15Lintel LevelUnder Progress11/24/2017 1:53:56 PM
10 BLY162113034BellaryInstitutionalSocialGeneralPreparation of platform and pavilion at Karnataka State Emergency Response Training Academy (Regional Home guards Training Centre) at Meenahalli village, Bellary talukaNK10/04/2016 13.91 04/10/201613.9113.914.85Finishing stageUnder Progress12/8/2017 11:58:54 AM
11 BLY162113036BellaryInstitutionalSocialGeneralProviding obstacles at Karnataka State Emergency Response Training Academy (Regional Home guards Training Centre) at Meenhalli village, Bellary talukaNK10/04/2016 30.50 04/10/201630.5030.5010.18Finishing stageUnder Progress11/24/2017 1:58:54 PM
12 BLY162113044BellaryInstitutionalEducationGeneralConstruction of Additional Class Room to Higher Primary School at Moka Bellary TalukaNK 25/02/2017 26.00 01/03/201726.0026.006.39Plinth Beam Completed Under Progress11/29/2017 11:27:22 AM
13 BLY162113081BellaryInfrastructureWater SupplyGeneralConstn of OHT and extension of pipeline at Chanalu village in Bellary TalukaRWS07/11/2016 32.46 22/12/201632.4631.990.00Laying of DI pipe completed. Construction of OHT under progressUnder Progress10/1/2017 1:45:56 PM
14 BLY162113089BellaryInstitutionalHostelGeneralConst of OBC Students Girls Hostel at Vijaynagar Sri. Krinadevarayya University Jnanasagara Campus Ballary.NK17/02/2017 180.14 09/03/2017179.45179.4519.89Basement completedUnder Progress11/24/2017 1:54:29 PM
15 BLY162123003BellaryInfrastructureRoads & BridgesGeneralImprovement of Road in Hanuman Nagar in Bellary CityCMC Bellary 05/11/2016 58.00 05/02/201758.0057.350.00Drain is completed. WBM LAYER IS LAID Under Progress11/30/2017 10:47:31 AM
16 BLY162123004BellaryInfrastructureRoads & BridgesGeneralImprovement to Road in Machgol Tippanna Layout Ward No. 20 (Behind Andhra KEB moka Road) in Bellary CityCMC Bellary 05/11/2016 29.00 05/02/201729.0028.610.00GRAVEL LAYING IS UNDER PROGRESSUnder Progress11/30/2017 10:55:13 AM
17 BLY162123005BellaryInfrastructureRoads & BridgesGeneralFormation of Drain at Diwakara Babu Layout in Ward No. 20 Bellary TalukaCMC Bellary 07/11/2016 70.00 05/02/201770.0069.230.00Construction of drain works are under progressUnder Progress10/20/2017 7:24:20 PM
18 BLY162123006BellaryInfrastructureRoads & BridgesGeneralImprovements to Roads at Mahateja Nagar in BellaryCMC Bellary 22/12/2016 66.80 22/12/201666.8061.270.00GSB LAYER IS COMPLETED .Under Progress11/30/2017 10:55:49 AM
19 BLY162123009BellaryInfrastructureRoads & BridgesGeneralDevelopment of road infront of Chaitanya School, Havambhavi Shiraguppa road in Bellary CityCMC Bellary 22/12/2016 69.00 22/12/201669.0068.770.00BM LAYER IS COMPLETED. Under Progress11/30/2017 10:58:46 AM
20 BLY162123014BellaryInfrastructureRoads & BridgesGeneralDevelopment of road at S N Pet Police Quarters main Bellary CityCMC Bellary 22/12/2016 11.01 22/12/201611.0110.970.00ROAD WORK COMPLETED. GATES TO BE FIXED.Under Progress11/30/2017 11:00:53 AM
21 BLY162123015BellaryInfrastructureRoads & BridgesGeneralProviding CC Road & Drain at Police Quarters in Millerpet Area in BellaryCMC Bellary 22/12/2016 39.36 22/12/201639.3638.660.00Drain works are completed and CC road is to be completed Under Progress10/20/2017 7:34:16 PM
22 BLY162123018BellaryInfrastructureRoads & BridgesGeneralConstruction of CC Road from Tinker Beedi culvert to Koul Bajar main road Mohammadi school beside big Drain in Bellary CityCMC Bellary 22/12/2016 47.50 22/12/201647.2346.810.00GSB LAYER LAID. WORK STOPPED DUE TO 24x7 WATER WORKS UNDER PROGRESSUnder Progress11/30/2017 11:02:16 AM
23 BLY162123019BellaryInfrastructureRoads & BridgesGeneralProviding and Constructing of RCC Drain and BT road in Hanuman Nagar From 8th Cross to Maruthi Nilaya Bellary CityCMC Bellary 22/12/2016 58.00 22/12/201657.7457.540.00Laying of BT Work is completed, part of drain work construction is in progress.Under Progress12/11/2017 4:33:35 PM
24 BLY162123022BellaryInfrastructureRoads & BridgesGeneralImprovement to Road at Guru Colony Ward No. 31 in Bellary CityCMC Bellary 25/01/2017 45.00 25/01/201742.8042.210.00GSB AND WMM LAYER LAIDUnder Progress11/30/2017 11:03:57 AM
25 BLY162123026BellaryInstitutionalEducationGeneralProviding RCC Roof to Existing class rooms and renovation at Govt. P.U. College, BellaryNK05/02/2017 164.10 05/02/2017164.10164.1018.35Roof work under progressUnder Progress11/22/2017 11:49:41 AM
26 BLY162123042BellaryInfrastructureUrban InfrastructureGeneralConstruction of Development work for Greve-Yard at Cowl Bazar, BellaryNK 21/04/2017 22.58 21/04/201722.5822.582.20Entrance Arch work and Platform work under progress Under Progress11/22/2017 11:56:27 AM
27 BLY162123043BellaryInfrastructureUrban InfrastructureGeneralConstruction of Compound Wall to Greve-Yard at Cowl Bazar, BellaryNK 21/04/2017 19.15 21/04/201719.1519.156.97finishing stageUnder Progress11/22/2017 11:56:38 AM
28 BLY162123060BellaryInstitutionalEducationGeneralConstruction of 3 Nos. Class rooms at Dasaranagenahalli in Bellary TalukaPRED-B 10/01/2017 21.00 08/03/201721.0019.830.00Roof levelUnder Progress11/20/2017 11:50:05 AM
29 BLY162423099BellaryInfrastructureRoads & BridgesGeneralಬಳ್ಳಾರಿ ಜಿಲ್ಲೆ ಬಳ್ಳಾರಿ ತಾಲ್ಲೂಕಿನ ಕೊಳಗಲ್ ಗ್ರಾಮ ಪಂಚಾಯ್ತಿ ವ್ಯಾಪ್ತಿಯ ಯರಂಗಳಿಗೆ ರಸ್ತೆಯಿಂದ ಕೃಷ್ಣ ನಗರ ಕ್ಯಾಂಪ್ ವರೆಗೆ ಕಾಮಗಾರಿPRED-B 14/12/2016 29.76 10/02/201729.7627.3316.00Metalling completedUnder Progress11/20/2017 11:53:23 AM
30 BLY162423100BellaryInfrastructureRoads & BridgesGeneralಬಳ್ಳಾರಿ ಜಿಲ್ಲೆ ಬಳ್ಳಾರಿ ತಾಲ್ಲೂಕಿನ ಕೊಳೂರು ಗ್ರಾಮ ಪಂಚಾಯ್ತಿ ವ್ಯಾಪ್ತಿಯ ಸಿ ಸಿ ರಸ್ತೆಗಳು ಮತ್ತು ಒಳಚರಂಡಿ ಕಾಮಗಾರಿPRED-B 14/12/2016 22.52 01/03/201722.5219.550.00Drain completed CC road under progressUnder Progress11/20/2017 11:53:58 AM
31 BLY162423101BellaryInfrastructureRoads & BridgesSCPಬಳ್ಳಾರಿ ಜಿಲ್ಲೆ ಬಳ್ಳಾರಿ ತಾಲ್ಲೂಕಿನ ಹೆಚ್ ವೀರಾಪುರ ಗ್ರಾಮ ಪಂಚಾಯ್ತಿ ವ್ಯಾಪ್ತಿಯ ಕೆರೆಕೆರೆಯಿಂದ ಚಿಟಿಗನಾಳ ಪಂಚಾಯ್ತಿವರೆಗಿನ ಕಾಮಗಾರಿPRED-B 14/12/2016 19.05 10/02/201719.0519.420.00Formation completedUnder Progress11/20/2017 11:54:21 AM
32 BLY163113039HospetInstitutionalEducationGeneralCnstn of compound wall to Govt high school Chittawadi in HospetNK25/02/2017 23.00 06/03/201723.0023.0010.7570% work completedUnder Progress11/22/2017 11:49:57 AM
33 BLY163113064HospetInstitutionalEducationGeneralConstruction of 4 Class rooms Govt. PU College (High School Divn.) TB Dam in Hospet TalukaPRED-B 22/11/2016 32.94 20/03/201734.2829.900.00Basement levelUnder Progress11/20/2017 11:55:38 AM
34 BLY163113065HospetInstitutionalEducationGeneralConstruction of Compound wall for play ground Govt. PU College (High School Divn.) TB Dam in Hospet TalukaPRED-B 22/11/2016 11.70 20/03/201711.7010.000.00Basement levelUnder Progress11/20/2017 11:56:05 AM
35 BLY163123076HospetInfrastructureRoads & BridgesGeneralFormation of approach road to Prouadha Devaraya Technical College in Hospet Taluka PWD-B 08/11/2016 102.50 05/02/201792.7084.560.00CC Drain on both side of road is under ProgressUnder Progress11/7/2017 6:34:55 PM
36 BLY166113048HadagaliInstitutionalParkGeneralConst of solar, lamp, benches, dustbin at August 15 park near Hoovinahadagali Bellary distNK 28/01/2017 11.33 28/01/201711.3311.330.96Benches fixing work completed. Other work returned to DC Office, BellaryUnder Progress11/22/2017 11:53:10 AM
37 BLY166123049HadagaliInfrastructureNemmadi UruGeneralNemmadi Uru Hadgali : Town HallNK 13/11/2016 186.86 28/01/2017184.29184.2930.84Basement CompletedUnder Progress11/22/2017 11:51:24 AM
38 BLY166123066HadagaliInfrastructureRoads & BridgesGeneralConstruction of Connectivity Road to Upanayakanhalli in Huvinahadagali TalukaPRED-H18/01/2017 37.88 18/01/201737.8835.620.00ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress10/24/2017 11:24:20 AM
39 BLY167123073H.B.HalliInfrastructureRoads & BridgesGeneralFormation of Approach road from Teru road to High school in Malvi village PRED-H08/11/2016 25.00 22/03/201723.7623.200.00ಪ್ರಾರಂಭಿಸಲಾಗಿದೆUnder Progress10/24/2017 11:31:04 AM
40 BLY167123074H.B.HalliInfrastructureRoads & BridgesGeneralFormation of road from Ganganna house to Devarkolli Hanumantappa house in Kenchanhallti villagePRED-H08/11/2016 25.00 22/03/201725.0024.140.00ಪ್ರಾರಂಭಿಸಲಾಗಿದೆUnder Progress10/24/2017 11:31:52 AM
         1928.17 1912.481878.39218.99